20 Years Ago June 27, 2003
The curbs and gutters on the west side of Greene Street are now being installed, but construction is moving slower than originally expected. The projected completion date for the project, which begins at 7th street and extends to 11th street, was initially July 17. But construction is already one and a half weeks behind schedule, and now the town is h...